At the Aardwarmte Polanen internet site in Monster , the Netherlands , building is in full swing these hebdomad . A squad of specialists is process close together on the next phase of the geothermal installment .
The day after Easter had been mark on the calendar for a long meter ; at 7:00 AM , large Crane tug onto the site . Because on this day , the large tanks that were already on the site were fix upright . What until recently were only drawings and calculations on newspaper is now becoming world , share Aardwarmte Polanen in a project update . with child tanks in placeApril 22 was a special milestone : several with child tanks were hoisted into place . ahead of time in the morn , the Harold Hart Crane were ready to set the first tank car – the balance tank – in its place . This tank , with a capacity of 100 cubic meters , had to be set good and cautiously bring down onto the orotund concrete disk on which it is climb . A precision labor for the crane operator and the support team .
After the balance tank , the enlargement tanks followed . Then it was the turn of the degasser : a horizontal tank car 15.5 meters long and with a diameter of 2.8 meter . This was mounted on the antecedently placed concrete supports . Within 10 minutes , this tankful was also exactly in place .

" you’re able to tell from everything that the preparation is pay off , " says construction coach Ruud Bruin . " Everyone knows what needs to be done , and it ’s marvelous to see how everything is now come together on the site . The installation is literally and figuratively taking bod . "
attend ahead : building and testingWith the location of these orotund components , a new phase has begun . In the coming month , the induction will be further built up . Among other things , the piping bridges will be installed , forming the connection between the various parts of the system . After the summertime , the interior of the construction will commence . Here , the filter , pumps , and warmth exchanger will find their place.23 horticultural entrepreneurs connected to Warmtenet PolanenIf everything pass away according to plan , testing of the instalment will begin at the end of 2025 . This brings sustainable rut provision for more horticultural entrepreneur in Westland ever nigher . In the neighborhood of the geothermic locating , piece of work is currently afoot on the construction of the Polanen estrus meshwork . In the future , 23 horticultural entrepreneurs will receive sustainable heat from Aardwarmte Polanen .
reference : Aardwarmte Polanen